Khurmala Dome
On July 18, 2009, the first oil from the Khurmala Dome Central Process Station was processed and transported by pipeline to supply the new 20,000 barrel per day Erbil Refinery.
The Khurmala Dome is the northern most dome of the Kirkuk oil field structure. The Dome is approximately 20 kilometers by 8 kilometers and lies fully on the territory of Erbil Governorate. During a meeting on November 24, 2008, between Kurdistan Regional Government Prime Minister Nechirvan Barzani and Iraqi Minister of Oil Dr. Hussein Al-Shahristani, it was jointly decided that the Khurmala Dome would be developed and operated to supply oil for the Erbil Refinery. KAR Oil & Gas Ltd. was chosen to build and operate the facilities.
KAR Oil & Gas has unique experience with the Khurmala Dome. In December 2004, KAR Oil & Gas was awarded an engineering and procurement contract by the Iraqi Ministry of Oil State Company for Oil Projects (SCOP). The 140 million USD contract was the first ever awarded to an Iraqi company for an oil field development project in Iraq. KAR sub-contracted DPS Engineering of Bristol, UK, to provide engineering expertise to bring the field to 100,000 barrels a day of production, and KAR led the effort to procure the massive equipment for the project. By early 2007, all equipment had arrived at Khurmala and was ready for installation and use, but no decision was taken to begin construction.
In late-November 2008, KAR Oil & Gas began fast-track construction of Phase One of the multi-phase project to bring the field to initial production by July 2009. KAR mobilized more than 1,000 team members, over 95 percent of whom were Iraqi, to build world standard facilities using the latest technologies. In a short seven months, KAR invested 150 million USD and achieved the Phase One goal of installing the equipment to produce 50,000 barrels of oil per day from the Khurmala Dome.
The Khurmala Dome is divided into three sections: North, Middle and South. In the North and Middle, KAR rehabilitated 40 previously drilled and capped wells to prepare them for production. 63 kilometers of flow lines were installed to connect the well heads to the manifold collectors that KAR installed at the North and Middle Stations. Test separators were installed at the North and Middle Stations allowing for precise well management and isolation for superior operations. Two 20 inch trunk lines, for a total of 14 kilometers, were built – one each from the North and Middle Stations to the Central Process Facility.
The Central Process Facility, approximately 200,000 square meters in size, was constructed with inlet collectors, production separators for separating the oil and associated gases, high and low pressure flares for gas flaring, pumps with capacity to push up to 225,000 barrels of oil per day, full health, safety and fire fighting systems and all infrastructure to rapidly scale the production facilities to 150,000 barrels a day of production. A 40 kilometer, 20 inch pipeline was installed and buried to carry oil from the Central Process Station to the Erbil Refinery.
KAR Oil & Gas will continue to add capacity and facilities at the Central Process Station to process up to 150,000 barrels of oil per day and 100 million standard cubic feet of gas. In the coming months, facilities will be added to capture the gas, process it and use it for industry such as power generation. Additional facilities to treat the oil, such as desalters and water treatment will also be installed.
KAR Oil & Gas is committed to a safe working environment. KAR’s health, safety and security systems are world standard, and since the inception of the project, no major accidents have been recorded.
KAR Oil & Gas is proud to be contributing to the development of the hydrocarbon sector in Iraq. In the past, the government did not allow local companies to participate in the oil sector, but the leadership of the Kurdistan Regional Government has enabled an environment that makes it possible for local companies to participate and lead in this vital industry. KAR Oil & Gas looks forward to the bright future it has in the ever dynamic hydrocarbon sector in Iraq.
FAST FACTS:
- The high Pressure flare is 55 meters in height
- The low pressure flare is 25 meters in height
- Phase 1 has 1.7 megawatts of power production and four transformers
- 30,000 meters of cable trays
- 3.5 kilometers of internal roads
- Accommodation for 300 persons
- 10,000 cubic meters of concrete
- 250,000 cubic meters of earth moved
- 45,000 dia-inch of pipe welding